| Assessment Year | 2017 |
|---|---|
| Principal Product | Wastewater treatment plant |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $50 M to 100M |
| # of Employees | 37 |
| Plant Area |
50,000
ft2
|
| Annual Production | 10,000,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $351,292 | 13,972,000 |
kWh
|
$0.025 |
| Electricity Demand | $516,032 | 29,698 |
kW-mo/yr
|
$17.38 |
| Electricity Fees | $98,484 | - |
|
- |
| Natural Gas | $40,000 | 10,075 |
MMBtu
|
$3.97 |
| TOTAL YEARLY COSTS | $1,005,808 | |||
| RECOMMENDED SAVINGS* | $82,498 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,052 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $24,750 | $80,000 | - | - |
$24,750
-
MMBtu
|
- | |
| 02 | 2.2628: Utilize a less expensive cooling method | $4,845 | $38,000 |
$2,343
103,200
kWh
|
$2,502
-
kW-mo/yr
|
- | - | |
| 03 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $26,851 | $133,000 |
$12,982
571,900
kWh
|
$13,869
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,766 | $97,500 |
$6,711
295,650
kWh
|
$14,075
-
kW-mo/yr
|
- | $2,980 | |
| 05 | 2.4151: Develop a repair/replace policy | $2,286 | $5,865 |
$891
39,257
kWh
|
$1,395
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $82,498 | $354,365 |
$22,927
1,010,007
kWh
|
$31,841
-
kW-mo/yr
|
$24,750
-
MMBtu
|
$2,980 | ||
| TOTAL IMPLEMENTED | $26,052 | $103,365 |
$7,602
334,907
kWh
|
$15,470
-
kW-mo/yr
|
- | $2,980 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs