Assessment Year | 1998 |
---|---|
Principal Product | Metal and Mylar Stamping |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
150,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,213 | 2,496,190 |
kWh
|
$0.059 |
Electricity Demand | $20,758 | 7,144 |
kW-mo/yr
|
$2.91 |
Electricity Fees | $11,194 | - |
|
- |
Natural Gas | $2,642 | 391 |
MMBtu
|
$6.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,416 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,995 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,912 | $23,975 |
$8,801
181,125
kWh
|
$3,111
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $318 | $377 |
$178
3,810
kWh
|
$34
-
kW-mo/yr
|
$33 | - | $73 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $819 | $822 |
$473
9,672
kWh
|
$346
-
kW-mo/yr
|
- | - | - | |
04 | 2.7261: Install timers and/or thermostats | $613 | $1,425 |
$613
12,603
kWh
|
- | - | - | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $6,835 | $11,600 |
$5,606
115,475
kWh
|
$1,229
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,005 | $240 |
$3,046
62,720
kWh
|
$959
-
kW-mo/yr
|
- | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $616 | $60 |
$616
12,603
kWh
|
- | - | - | - | |
08 | 3.6192: Use a less expensive method of waste removal | $525 | $60 | - | - | - | $525 | - | |
09 | 4.514: Re-arrange equipment layout to reduce handling costs | $12,854 | $450 |
$10,088
207,503
kWh
|
$2,766
-
kW-mo/yr
|
- | - | - | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $6,919 | $9,000 |
$(-827.0)
(-16,999)
kWh
|
$(-692.0)
-
kW-mo/yr
|
$8,438 | - | - | |
TOTAL RECOMMENDED | $45,416 | $48,009 |
$28,594
588,512
kWh
|
$7,753
-
kW-mo/yr
|
$8,471 | $525 | $73 | ||
TOTAL IMPLEMENTED | $25,995 | $25,910 |
$20,118
413,834
kWh
|
$5,877
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs