Assessment Year | 2017 |
---|---|
Principal Product | Fresh herbs |
NAICS | 311942: Spice and Extract Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
340,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $252,742 | 4,764,630 |
kWh
|
$0.053 |
Electricity Demand | $100,768 | 24,121 |
kW-mo/yr
|
$4.18 |
Electricity Fees | $2,189 | - |
|
- |
LPG | $261,368 | 26,948 |
MMBtu
|
$9.70 |
TOTAL YEARLY COSTS | $617,067 | |||
RECOMMENDED SAVINGS* | $947,122 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $947,122 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,081 | $2,500 | - |
$3,081
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $308 | $200 |
$277
5,424
kWh
|
$31
-
kW-mo/yr
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $988 | $2,500 |
$885
17,318
kWh
|
$103
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,873 | $9,000 |
$7,593
148,587
kWh
|
$886
-
kW-mo/yr
|
$1,394 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $929,030 | $400,000 |
$27,496
538,083
kWh
|
- | $21,534 | $880,000 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,008 | $2,890 |
$872
17,069
kWh
|
- | $136 | - | |
07 | 2.4151: Develop a repair/replace policy | $2,834 | $4,685 |
$2,552
49,940
kWh
|
$282
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $947,122 | $421,775 |
$39,675
776,421
kWh
|
$4,383
-
kW-mo/yr
|
$23,064 | $880,000 | ||
TOTAL IMPLEMENTED | $947,122 | $421,775 |
$39,675
776,421
kWh
|
$4,383
-
kW-mo/yr
|
$23,064 | $880,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs