Assessment Year | 2017 |
---|---|
Principal Product | Milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
96,000
ft2
|
Annual Production | 33,000
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $664,426 | 8,586,312 |
kWh
|
$0.077 |
Electricity Demand | $124,537 | 22,607 |
kW-mo/yr
|
$5.51 |
Electricity Fees | $651 | - |
|
- |
Natural Gas | $185,200 | 39,000 |
MMBtu
|
$4.75 |
TOTAL YEARLY COSTS | $974,814 | |||
RECOMMENDED SAVINGS* | $80,527 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,738 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $61,111 | $160,000 |
$6,230
81,438
kWh
|
$636
-
kW-mo/yr
|
$54,245
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,519 | $6,412 |
$5,573
72,848
kWh
|
$568
-
kW-mo/yr
|
- | - | $378 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,025 | $200 |
$1,484
19,400
kWh
|
$321
-
kW-mo/yr
|
- | $(-300.0) | $(-480.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,222 | $100 |
$1,830
23,920
kWh
|
$392
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $6,456 | $7,000 | - | - |
$6,456
-
MMBtu
|
- | - | |
06 | 2.4151: Develop a repair/replace policy | $2,529 | $5,865 |
$2,082
27,218
kWh
|
$447
-
kW-mo/yr
|
- | - | - | |
07 | 2.2123: Insulate feedwater tank | $665 | $1,106 | - | - |
$665
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $80,527 | $180,683 |
$17,199
224,824
kWh
|
$2,364
-
kW-mo/yr
|
$61,366
-
MMBtu
|
$(-300.0) | $(-102.0) | ||
TOTAL IMPLEMENTED | $10,738 | $13,583 |
$9,139
119,466
kWh
|
$1,336
-
kW-mo/yr
|
$665
-
MMBtu
|
$(-300.0) | $(-102.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs