Assessment Year | 2016 |
---|---|
Principal Product | Specialty fabrics |
NAICS | 313210: Broadwoven Fabric Mills |
SIC | 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing) |
Sales Range | $100 M to 500M |
# of Employees | 229 |
Plant Area |
225,000
ft2
|
Annual Production | 2,385,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $561,411 | 12,105,527 |
kWh
|
$0.046 |
Electricity Demand | $286,872 | 28,434 |
kW-mo/yr
|
$10.09 |
Electricity Fees | $408 | - |
|
- |
Natural Gas | $701,092 | 169,054 |
MMBtu
|
$4.15 |
TOTAL YEARLY COSTS | $1,549,783 | |||
RECOMMENDED SAVINGS* | $150,485 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $119,915 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $52,901 | $500 |
$52,901
-
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $46,532 | $113,706 |
$28,584
616,033
kWh
|
$13,873
-
kW-mo/yr
|
- | - | $4,075 | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $17,247 | $50,000 |
$16,701
360,000
kWh
|
$7,337
-
kW-mo/yr
|
$(-6,791.0)
-
MMBtu
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,076 | $200 |
$4,776
102,948
kWh
|
$2,100
-
kW-mo/yr
|
- | $(-500.0) | $(-300.0) | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,661 | $8,900 |
$4,628
99,751
kWh
|
$2,033
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,575 | $3,000 |
$571
12,309
kWh
|
$1,004
-
kW-mo/yr
|
- | - | - | |
07 | 2.2437: Recover waste heat from equipment | $4,983 | $4,000 | - | - |
$4,983
-
MMBtu
|
- | - | |
08 | 2.4151: Develop a repair/replace policy | $2,622 | $5,865 |
$1,822
39,257
kWh
|
$800
-
kW-mo/yr
|
- | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,679 | $230 |
$1,167
25,154
kWh
|
$512
-
kW-mo/yr
|
- | - | - | |
10 | 2.2113: Repair or replace steam traps | $7,750 | $8,500 | - | - |
$12,450
-
MMBtu
|
$(-1,250.0) | $(-3,450.0) | |
11 | 2.2135: Repair and eliminate steam leaks | $2,459 | $1,000 | - | - |
$2,459
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $150,485 | $195,901 |
$111,150
1,255,452
kWh
|
$27,659
-
kW-mo/yr
|
$13,101
-
MMBtu
|
$(-1,750.0) | $325 | ||
TOTAL IMPLEMENTED | $119,915 | $132,771 |
$88,654
770,547
kWh
|
$17,777
-
kW-mo/yr
|
$14,909
-
MMBtu
|
$(-1,750.0) | $325 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs