Assessment Year | 2016 |
---|---|
Principal Product | Brass plumbing fittings |
NAICS | 332913: Plumbing Fixture Fitting and Trim Manufacturing |
SIC | 3432: Plumbing Fixture Fittings and Trim |
Sales Range | $100 M to 500M |
# of Employees | 370 |
Plant Area |
304,000
ft2
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,068,235 | 32,141,282 |
kWh
|
$0.064 |
Electricity Demand | $124,350 | 100,908 |
kW-mo/yr
|
$1.23 |
Natural Gas | $644,389 | 105,426 |
MMBtu
|
$6.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $123,077 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,201 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $47,821 | $40,000 |
$47,821
743,710
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $21,093 | $200 |
$21,873
340,176
kWh
|
$(-300.0) | $(-480.0) | |
03 | 2.2612: Use cooling tower water instead of refrigeration | $29,861 | $3,000 |
$29,861
541,800
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,108 | $100 |
$10,108
157,200
kWh
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $12,750 | $8,750 |
$12,750
198,750
kWh
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $399 | $900 |
$399
6,210
kWh
|
- | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,045 | $900 |
$1,045
14,688
kWh
|
- | - | |
TOTAL RECOMMENDED | $123,077 | $53,850 |
$123,857
2,002,534
kWh
|
$(-300.0) | $(-480.0) | ||
TOTAL IMPLEMENTED | $31,201 | $300 |
$31,981
497,376
kWh
|
$(-300.0) | $(-480.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs