ITAC Assessment: NC0559
ITAC logo
ITAC Assessment: NC0559
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Carbon fiber
NAICS 325220: Artificial and Synthetic Fibers and Filaments Manufacturing
SIC 2823: Cellulosic Manmade Fibers
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 250,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,638,639 42,868,867
kWh
Electricity Demand $643,355 67,211
kW-mo/yr
Natural Gas $906,898 198,587
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $241,580 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $180,337

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $109,787 $1,000 $109,787
-
kWh
- - - -
02 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $28,202 $75,000 $33,329
872,496
kWh
$11,438
-
kW-mo/yr
$(-16,565.0)
-
MMBtu
- -
03 2.5122: Replace high resistance ducts, pipes, and fittings $4,003 $1,000 $374
9,802
kWh
$129
-
kW-mo/yr
- - $3,500
04 2.2614: Use cooling tower or economizer to replace chiller cooling $5,720 $10,000 $4,258
111,480
kWh
$1,462
-
kW-mo/yr
- - -
05 2.2127: Flash condensate to produce lower pressure steam $20,410 $15,050 - - $20,410
-
MMBtu
- -
06 2.1243: Use heat from boiler blowdown to preheat boiler feed water $9,950 $25,000 - - $9,950
-
MMBtu
- -
07 2.2628: Utilize a less expensive cooling method $34,146 $10,000 $1,873
49,030
kWh
$643
-
kW-mo/yr
$31,630
-
MMBtu
- -
08 2.2135: Repair and eliminate steam leaks $7,231 $2,000 - - $7,231
-
MMBtu
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,038 $320 $326
8,540
kWh
$113
-
kW-mo/yr
- - $599
10 2.7134: Use photocell controls $1,339 $1,600 $1,339
35,040
kWh
- - - -
11 2.7135: Install occupancy sensors $494 $347 $494
12,930
kWh
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $2,545 $8,000 $2,677
70,080
kWh
- - - $(-132.0)
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,085 $1,000 $9,145
239,400
kWh
$3,140
-
kW-mo/yr
- $(-1,000.0) $(-1,200.0)
14 2.4239: Eliminate or reduce compressed air usage $4,366 $1,800 $2,996
78,420
kWh
$1,370
-
kW-mo/yr
- - -
15 2.4151: Develop a repair/replace policy $2,264 $4,256 $1,685
44,123
kWh
$579
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $241,580 $156,373 $168,283
1,531,341
kWh
$18,874
-
kW-mo/yr
$52,656
-
MMBtu
$(-1,000.0) $2,767
TOTAL IMPLEMENTED $180,337 $46,523 $125,023
398,865
kWh
$4,604
-
kW-mo/yr
$48,811
-
MMBtu
$(-1,000.0) $2,899
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs