Assessment Year | 2023 |
---|---|
Principal Product | Model Rocket Engines |
NAICS | 333249: Other Industrial Machinery Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
133,500
ft2
|
Annual Production | 150,000
units
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,761 | 882,400 |
kWh
|
$0.067 |
Electricity Demand | $68,393 | 3,542 |
kW-mo/yr
|
$19.31 |
Electricity Fees | $12,149 | - |
|
- |
Natural Gas | $55,854 | 6,237 |
MMBtu
|
$8.96 |
TOTAL YEARLY COSTS | $195,157 | |||
RECOMMENDED SAVINGS* | $45,766 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,152 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $28,381 | $291,962 |
$25,137
377,472
kWh
|
$3,244
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,939 | $6,474 |
$2,518
37,820
kWh
|
$3,421
-
kW-mo/yr
|
- | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $2,832 | $36,480 |
$1,255
18,827
kWh
|
$1,411
-
kW-mo/yr
|
$166
-
MMBtu
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $843 | $17,694 |
$387
5,797
kWh
|
$456
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $760 | $75 |
$335
5,016
kWh
|
$425
-
kW-mo/yr
|
- | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $7,011 | $8,000 | - | - | - | $7,011 | |
TOTAL RECOMMENDED | $45,766 | $360,685 |
$29,632
444,932
kWh
|
$8,957
-
kW-mo/yr
|
$166
-
MMBtu
|
$7,011 | ||
TOTAL IMPLEMENTED | $37,152 | $334,916 |
$28,910
434,119
kWh
|
$8,076
-
kW-mo/yr
|
$166
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs