ITAC Assessment: MS0457
ITAC logo
ITAC Assessment: MS0457
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Thermoplastic Resins
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $50
M
to 100
M
# of Employees 115
Plant Area 700,000
ft2
Annual Production 70,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $805,095 11,452,828
kWh
Electricity Demand $157,390 19,078
kW-mo/yr
Electricity Fees $74,809 -
Natural Gas $935,333 222,169
MMBtu
LPG $7,542 228
MMBtu
TOTAL YEARLY COSTS $1,980,169
RECOMMENDED SAVINGS* $72,546 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings LPG Savings
01 2.4321: Upgrade obsolete equipment $6,840 $29,366 $6,840
97,717
kWh
- -
02 2.1321: Replace fossil fuel equipment with electrical equipment $9,586 $75,000 $2,044
29,200
kWh
- $7,542
-
MMBtu
03 2.1221: Replace obsolete burners with more efficient ones $56,120 $321,000 - $56,120
-
MMBtu
-
TOTAL RECOMMENDED $72,546 $425,366 $8,884
126,917
kWh
$56,120
-
MMBtu
$7,542
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs