ITAC Assessment: NC0556
ITAC logo
ITAC Assessment: NC0556
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Ceramic stovetops
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 160,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,104,518 28,104,000
kWh
Electricity Demand $552,976 50,854
kW-mo/yr
Natural Gas $19,665 2,469
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $59,808 $90,000 $38,404
984,720
kWh
$21,404
-
kW-mo/yr
-
02 2.4239: Eliminate or reduce compressed air usage $2,806 $5,000 $1,802
46,200
kWh
$1,004
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,438 $12,000 $6,438
165,072
kWh
- -
04 2.2437: Recover waste heat from equipment $9,076 $3,200 $5,828
149,429
kWh
$3,248
-
kW-mo/yr
-
05 2.4151: Develop a repair/replace policy $1,836 $4,256 $1,179
30,221
kWh
$657
-
kW-mo/yr
-
06 2.3132: Recharge batteries on during off-peak demand periods $1,228 $200 $1,228
-
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,584 $8,350 $2,247
57,612
kWh
$1,252
-
kW-mo/yr
$(-915.0)
08 2.7135: Install occupancy sensors $578 $868 $578
14,829
kWh
- -
TOTAL RECOMMENDED $84,354 $123,874 $57,704
1,448,083
kWh
$27,565
-
kW-mo/yr
$(-915.0)
TOTAL IMPLEMENTED $71,244 $115,474 $48,846
1,252,454
kWh
$23,313
-
kW-mo/yr
$(-915.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs