Assessment Year | 2015 |
---|---|
Principal Product | Ceramic stovetops |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
160,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,104,518 | 28,104,000 |
kWh
|
$0.039 |
Electricity Demand | $552,976 | 50,854 |
kW-mo/yr
|
$10.87 |
Natural Gas | $19,665 | 2,469 |
MMBtu
|
$7.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $71,244 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $59,808 | $90,000 |
$38,404
984,720
kWh
|
$21,404
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $2,806 | $5,000 |
$1,802
46,200
kWh
|
$1,004
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,438 | $12,000 |
$6,438
165,072
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $9,076 | $3,200 |
$5,828
149,429
kWh
|
$3,248
-
kW-mo/yr
|
- | |
05 | 2.4151: Develop a repair/replace policy | $1,836 | $4,256 |
$1,179
30,221
kWh
|
$657
-
kW-mo/yr
|
- | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $1,228 | $200 |
$1,228
-
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,584 | $8,350 |
$2,247
57,612
kWh
|
$1,252
-
kW-mo/yr
|
$(-915.0) | |
08 | 2.7135: Install occupancy sensors | $578 | $868 |
$578
14,829
kWh
|
- | - | |
TOTAL RECOMMENDED | $84,354 | $123,874 |
$57,704
1,448,083
kWh
|
$27,565
-
kW-mo/yr
|
$(-915.0) | ||
TOTAL IMPLEMENTED | $71,244 | $115,474 |
$48,846
1,252,454
kWh
|
$23,313
-
kW-mo/yr
|
$(-915.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs