Assessment Year | 2015 |
---|---|
Principal Product | Steering and suspension parts |
NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 330 |
Plant Area |
144,000
ft2
|
Annual Production | 16,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $397,871 | 6,674,596 |
kWh
|
$0.060 |
Electricity Demand | $155,485 | 12,715 |
kW-mo/yr
|
$12.23 |
Natural Gas | $119,480 | 14,043 |
MMBtu
|
$8.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $144,839 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $75,788 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $64,078 | $68,997 |
$46,472
774,534
kWh
|
$17,381
-
kW-mo/yr
|
- | - | - | $225 | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $28,971 | $40,000 |
$21,273
354,556
kWh
|
$19,523
-
kW-mo/yr
|
$(-11,825.0)
-
MMBtu
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,402 | $100 |
$6,043
100,710
kWh
|
$2,259
-
kW-mo/yr
|
- | - | $(-600.0) | $(-300.0) | |
04 | 2.2437: Recover waste heat from equipment | $7,041 | $10,000 |
$4,028
67,140
kWh
|
$3,013
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $7,738 | $6,000 |
$5,632
93,862
kWh
|
$2,106
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,805 | $100 |
$2,769
46,158
kWh
|
$1,036
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $9,398 | $21,800 |
$6,840
114,000
kWh
|
$2,558
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.6242: Minimize operation of equipment maintained in standby condition | $192 | $500 |
$192
3,198
kWh
|
- | - | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $311 | $80 |
$128
2,137
kWh
|
$33
-
kW-mo/yr
|
- | - | - | $150 | |
10 | 2.6218: Turn off equipment when not in use | $8,618 | $20,000 |
$8,618
143,640
kWh
|
- | - | - | - | - | |
11 | 2.4151: Develop a repair/replace policy | $2,491 | $4,256 |
$1,813
30,211
kWh
|
$678
-
kW-mo/yr
|
- | - | - | - | |
12 | 3.3131: Use evaporation to concentrate material | $4,794 | $19,000 | - | - |
$(-1,287.0)
-
MMBtu
|
$6,081
-
lb
|
- | - | |
TOTAL RECOMMENDED | $144,839 | $190,833 |
$103,808
1,730,146
kWh
|
$48,587
-
kW-mo/yr
|
$(-13,112.0)
-
MMBtu
|
$6,081
-
lb
|
$(-600.0) | $75 | ||
TOTAL IMPLEMENTED | $75,788 | $69,777 |
$55,604
926,737
kWh
|
$20,709
-
kW-mo/yr
|
- | - | $(-600.0) | $75 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs