Assessment Year | 2014 |
---|---|
Principal Product | Air filters |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 640 |
Plant Area |
521,523
ft2
|
Annual Production | 33,000,000
pieces
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $275,917 | 5,237,297 |
kWh
|
$0.053 |
Electricity Demand | $99,128 | 11,650 |
kW-mo/yr
|
$8.51 |
Electricity Fees | $1,647 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,957 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,402 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $14,069 | $54,000 |
$14,069
266,964
kWh
|
- | - | - | |
02 | 2.3135: Schedule routine maintenance during non-operating periods | $1,055 | - | - |
$1,055
-
kW-mo/yr
|
- | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $1,962 | $200 |
$440
-
kWh
|
$1,522
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,946 | $18,000 |
$4,946
93,844
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,542 | $5,000 |
$1,888
35,818
kWh
|
$654
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $443 | $200 |
$594
11,280
kWh
|
$209
-
kW-mo/yr
|
$(-200.0) | $(-160.0) | |
07 | 2.4239: Eliminate or reduce compressed air usage | $1,767 | $4,000 |
$534
10,141
kWh
|
$1,233
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,623 | $2,350 |
$1,724
32,710
kWh
|
$654
-
kW-mo/yr
|
- | $245 | |
09 | 2.7135: Install occupancy sensors | $2,127 | $6,420 |
$2,127
40,364
kWh
|
- | - | - | |
10 | 2.7111: Reduce illumination to minimum necessary levels | $686 | $563 |
$425
8,064
kWh
|
$147
-
kW-mo/yr
|
- | $114 | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $632 | $176 |
$248
4,702
kWh
|
$55
-
kW-mo/yr
|
- | $329 | |
12 | 2.7134: Use photocell controls | $341 | $80 |
$341
6,480
kWh
|
- | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $763 | $2,400 |
$528
10,021
kWh
|
$235
-
kW-mo/yr
|
- | - | |
14 | 2.4151: Develop a repair/replace policy | $2,001 | $4,256 |
$1,487
28,207
kWh
|
$514
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $35,957 | $97,645 |
$29,351
548,595
kWh
|
$6,278
-
kW-mo/yr
|
$(-200.0) | $528 | ||
TOTAL IMPLEMENTED | $9,402 | $7,745 |
$4,918
84,963
kWh
|
$4,156
-
kW-mo/yr
|
$(-200.0) | $528 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs