ITAC Assessment: ME0105
ITAC logo
ITAC Assessment: ME0105
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Canoes
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 100,000
ft2
Annual Production 29,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,149 1,080,598
kWh
Fuel Oil #2 $79,252 17,893
MMBtu
Fuel Oil #6 $28,737 13,247
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,312 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,466

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.4133: Use most efficient type of electric motors $2,631 $1,344 $2,631
25,791
kWh
-
02 2.2414: Use waste heat from hot flue gases to preheat $14,846 $22,500 - $14,846
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $579 $1,405 $579
5,569
kWh
-
04 2.1211: Move boiler to more efficient location $256 $200 $256
1,758
kWh
-
TOTAL RECOMMENDED $18,312 $25,449 $3,466
33,118
kWh
$14,846
-
MMBtu
TOTAL IMPLEMENTED $3,466 $2,949 $3,466
33,118
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs