ITAC Assessment: NC0524
ITAC logo
ITAC Assessment: NC0524
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product HVAC compressors
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 800,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,816,948 44,467,783
kWh
Electricity Demand $1,321,382 100,718
kW-mo/yr
Natural Gas $523,564 114,230
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,447 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,106

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,264 $42,866 $7,494
182,784
kWh
$7,195
-
kW-mo/yr
- - $(-425.0)
02 2.4231: Reduce the pressure of compressed air to the minimum required $19,056 $100 $9,723
237,137
kWh
$9,333
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,368 $100 $6,515
158,898
kWh
$6,253
-
kW-mo/yr
- $(-1,200.0) $(-1,200.0)
04 2.4131: Size electric motors for peak operating efficiency $7,341 $29,000 $7,341
179,040
kWh
- - - -
05 2.4239: Eliminate or reduce compressed air usage $606 $300 $309
7,540
kWh
$297
-
kW-mo/yr
- - -
06 2.7111: Reduce illumination to minimum necessary levels $3,243 $475 $1,432
34,920
kWh
$1,375
-
kW-mo/yr
- - $436
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,355 $3,984 $1,201
29,304
kWh
$1,154
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $1,948 $3,644 $1,948
47,504
kWh
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $550 $160 $175
4,275
kWh
$77
-
kW-mo/yr
- - $298
10 2.7134: Use photocell controls $54 $40 $54
1,320
kWh
- - - -
11 2.2135: Repair and eliminate steam leaks $1,126 $1,050 - - $1,126
-
MMBtu
- -
12 2.4151: Develop a repair/replace policy $2,718 $8,146 $1,382
33,944
kWh
$1,336
-
kW-mo/yr
- - -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $818 $180 $417
10,174
kWh
$401
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $64,447 $90,045 $37,991
926,840
kWh
$27,421
-
kW-mo/yr
$1,126
-
MMBtu
$(-1,200.0) $(-891.0)
TOTAL IMPLEMENTED $57,106 $61,045 $30,650
747,800
kWh
$27,421
-
kW-mo/yr
$1,126
-
MMBtu
$(-1,200.0) $(-891.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs