Assessment Year | 2014 |
---|---|
Principal Product | HVAC compressors |
NAICS | 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen |
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
800,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,816,948 | 44,467,783 |
kWh
|
$0.041 |
Electricity Demand | $1,321,382 | 100,718 |
kW-mo/yr
|
$13.12 |
Natural Gas | $523,564 | 114,230 |
MMBtu
|
$4.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,106 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,264 | $42,866 |
$7,494
182,784
kWh
|
$7,195
-
kW-mo/yr
|
- | - | $(-425.0) | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,056 | $100 |
$9,723
237,137
kWh
|
$9,333
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,368 | $100 |
$6,515
158,898
kWh
|
$6,253
-
kW-mo/yr
|
- | $(-1,200.0) | $(-1,200.0) | |
04 | 2.4131: Size electric motors for peak operating efficiency | $7,341 | $29,000 |
$7,341
179,040
kWh
|
- | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $606 | $300 |
$309
7,540
kWh
|
$297
-
kW-mo/yr
|
- | - | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $3,243 | $475 |
$1,432
34,920
kWh
|
$1,375
-
kW-mo/yr
|
- | - | $436 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,355 | $3,984 |
$1,201
29,304
kWh
|
$1,154
-
kW-mo/yr
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $1,948 | $3,644 |
$1,948
47,504
kWh
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $550 | $160 |
$175
4,275
kWh
|
$77
-
kW-mo/yr
|
- | - | $298 | |
10 | 2.7134: Use photocell controls | $54 | $40 |
$54
1,320
kWh
|
- | - | - | - | |
11 | 2.2135: Repair and eliminate steam leaks | $1,126 | $1,050 | - | - |
$1,126
-
MMBtu
|
- | - | |
12 | 2.4151: Develop a repair/replace policy | $2,718 | $8,146 |
$1,382
33,944
kWh
|
$1,336
-
kW-mo/yr
|
- | - | - | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $818 | $180 |
$417
10,174
kWh
|
$401
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $64,447 | $90,045 |
$37,991
926,840
kWh
|
$27,421
-
kW-mo/yr
|
$1,126
-
MMBtu
|
$(-1,200.0) | $(-891.0) | ||
TOTAL IMPLEMENTED | $57,106 | $61,045 |
$30,650
747,800
kWh
|
$27,421
-
kW-mo/yr
|
$1,126
-
MMBtu
|
$(-1,200.0) | $(-891.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs