Assessment Year | 2014 |
---|---|
Principal Product | Rebuilt engines |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 91 |
Plant Area |
36,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,450 | 716,400 |
kWh
|
$0.068 |
Electricity Demand | $16,700 | 3,975 |
kW-mo/yr
|
$4.20 |
Electricity Fees | $2,135 | - |
|
- |
Natural Gas | $36,750 | 4,022 |
MMBtu
|
$9.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,611 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,237 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $3,379 | $6,500 | - | - |
$900
-
MMBtu
|
$2,479
-
Tgal
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,436 | $5,000 |
$4,869
72,021
kWh
|
$2,381
-
kW-mo/yr
|
$(-2,814.0)
-
MMBtu
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,823 | $1,500 |
$2,378
35,183
kWh
|
$445
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $2,016 | $3,500 | - | - |
$2,016
-
MMBtu
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $207 | $100 |
$393
5,819
kWh
|
$74
-
kW-mo/yr
|
- | - | $(-100.0) | $(-160.0) | |
06 | 2.2437: Recover waste heat from equipment | $472 | $320 |
$231
3,420
kWh
|
$241
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $439 | $309 |
$370
5,472
kWh
|
$69
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $797 | $208 |
$376
5,558
kWh
|
$32
-
kW-mo/yr
|
- | - | - | $389 | |
09 | 2.7135: Install occupancy sensors | $455 | $400 |
$455
6,732
kWh
|
- | - | - | - | - | |
10 | 2.4151: Develop a repair/replace policy | $1,616 | $4,256 |
$1,362
20,148
kWh
|
$254
-
kW-mo/yr
|
- | - | - | - | |
11 | 3.4111: Use closed cycle process to minimize waste water production | $971 | $3,500 |
$(-30.0)
(-443)
kWh
|
$(-52.0)
-
kW-mo/yr
|
- |
$1,053
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $17,611 | $25,593 |
$10,404
153,910
kWh
|
$3,444
-
kW-mo/yr
|
$102
-
MMBtu
|
$3,532
-
Tgal
|
$(-100.0) | $229 | ||
TOTAL IMPLEMENTED | $5,237 | $5,617 |
$3,487
51,589
kWh
|
$568
-
kW-mo/yr
|
- |
$1,053
-
Tgal
|
$(-100.0) | $229 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs