Assessment Year | 2014 |
---|---|
Principal Product | Paperboard packaging |
NAICS | 322212: Folding Paperboard Box Manufacturing |
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $50 M to 100M |
# of Employees | 280 |
Plant Area |
173,200
ft2
|
Annual Production | 63,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $421,813 | 10,444,356 |
kWh
|
$0.040 |
Electricity Demand | $257,450 | 24,712 |
kW-mo/yr
|
$10.42 |
Natural Gas | $20,956 | 2,459 |
MMBtu
|
$8.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,167 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,082 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,219 | $80,659 |
$13,001
325,033
kWh
|
$6,218
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,056 | $22,494 |
$8,237
205,918
kWh
|
$3,065
-
kW-mo/yr
|
- | $(-246.0) | |
03 | 2.7135: Install occupancy sensors | $2,633 | $5,706 |
$2,633
65,829
kWh
|
- | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,255 | $413 |
$816
20,412
kWh
|
$304
-
kW-mo/yr
|
- | $135 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,324 | $400 |
$428
10,688
kWh
|
$152
-
kW-mo/yr
|
- | $744 | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,992 | $100 |
$4,032
100,800
kWh
|
$1,500
-
kW-mo/yr
|
$(-300.0) | $(-240.0) | |
07 | 2.4151: Develop a repair/replace policy | $3,912 | $8,146 |
$2,851
71,283
kWh
|
$1,061
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,173 | $23 |
$855
21,366
kWh
|
$318
-
kW-mo/yr
|
- | - | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,603 | $200 |
$570
-
kWh
|
$1,033
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $47,167 | $118,141 |
$33,423
821,329
kWh
|
$13,651
-
kW-mo/yr
|
$(-300.0) | $393 | ||
TOTAL IMPLEMENTED | $42,082 | $109,972 |
$29,717
728,680
kWh
|
$12,272
-
kW-mo/yr
|
$(-300.0) | $393 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs