ITAC Assessment: NC0520
ITAC logo
ITAC Assessment: NC0520
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Paperboard packaging
NAICS 322212: Folding Paperboard Box Manufacturing
SIC 2657: Folding Paperboard Boxes, Including Sanitary
Sales Range $50
M
to 100
M
# of Employees 280
Plant Area 173,200
ft2
Annual Production 63,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $421,813 10,444,356
kWh
Electricity Demand $257,450 24,712
kW-mo/yr
Natural Gas $20,956 2,459
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,167 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,082

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $19,219 $80,659 $13,001
325,033
kWh
$6,218
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,056 $22,494 $8,237
205,918
kWh
$3,065
-
kW-mo/yr
- $(-246.0)
03 2.7135: Install occupancy sensors $2,633 $5,706 $2,633
65,829
kWh
- - -
04 2.7111: Reduce illumination to minimum necessary levels $1,255 $413 $816
20,412
kWh
$304
-
kW-mo/yr
- $135
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,324 $400 $428
10,688
kWh
$152
-
kW-mo/yr
- $744
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,992 $100 $4,032
100,800
kWh
$1,500
-
kW-mo/yr
$(-300.0) $(-240.0)
07 2.4151: Develop a repair/replace policy $3,912 $8,146 $2,851
71,283
kWh
$1,061
-
kW-mo/yr
- -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,173 $23 $855
21,366
kWh
$318
-
kW-mo/yr
- -
09 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,603 $200 $570
-
kWh
$1,033
-
kW-mo/yr
- -
TOTAL RECOMMENDED $47,167 $118,141 $33,423
821,329
kWh
$13,651
-
kW-mo/yr
$(-300.0) $393
TOTAL IMPLEMENTED $42,082 $109,972 $29,717
728,680
kWh
$12,272
-
kW-mo/yr
$(-300.0) $393
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs