Assessment Year | 2014 |
---|---|
Principal Product | Whipped cream and freezer pops |
NAICS | 311412: Frozen Specialty Food Manufacturing |
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
65,000
ft2
|
Annual Production | 35,200,000
pieces
|
Production Hrs. Annual | 7,800
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $192,003 | 4,932,900 |
kWh
|
$0.039 |
Electricity Demand | $120,525 | 10,440 |
kW-mo/yr
|
$11.54 |
Natural Gas | $147,356 | 28,014 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,276,268 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,264,997 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $1,248,000 | $800,000 | - | - | - | $1,248,000 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,224 | $50 |
$5,581
143,120
kWh
|
$2,643
-
kW-mo/yr
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $824 | $1,750 | - | - |
$824
-
MMBtu
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,276 | $100 |
$1,640
42,042
kWh
|
$776
-
kW-mo/yr
|
- | $(-900.0) | $(-240.0) | |
05 | 2.4239: Eliminate or reduce compressed air usage | $3,126 | $5,000 |
$2,122
54,405
kWh
|
$1,004
-
kW-mo/yr
|
- | - | - | |
06 | 2.2444: Use hot process fluids to preheat incoming process fluids | $7,321 | $15,000 | - | - |
$7,321
-
MMBtu
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $524 | $100 |
$255
-
kWh
|
$269
-
kW-mo/yr
|
- | - | - | |
08 | 2.4151: Develop a repair/replace policy | $2,258 | $4,256 |
$1,532
39,288
kWh
|
$726
-
kW-mo/yr
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,951 | $7,604 |
$1,238
31,741
kWh
|
$713
-
kW-mo/yr
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,688 | $3,708 |
$1,158
29,702
kWh
|
$549
-
kW-mo/yr
|
- | - | $(-19.0) | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $536 | $160 |
$167
4,275
kWh
|
$70
-
kW-mo/yr
|
- | - | $299 | |
12 | 2.7134: Use photocell controls | $103 | $80 |
$103
2,640
kWh
|
- | - | - | - | |
13 | 2.7135: Install occupancy sensors | $437 | $774 |
$437
11,213
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,276,268 | $838,582 |
$14,233
358,426
kWh
|
$6,750
-
kW-mo/yr
|
$8,145
-
MMBtu
|
$1,247,100 | $40 | ||
TOTAL IMPLEMENTED | $1,264,997 | $816,832 |
$12,111
304,021
kWh
|
$5,746
-
kW-mo/yr
|
- | $1,247,100 | $40 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs