ITAC Assessment: NC0499
ITAC logo
ITAC Assessment: NC0499
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Dyed and finished fabrics
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2262: Finishers of Broadwoven Fabrics of Manmade Fiber and Silk
Sales Range $50
M
to 100
M
# of Employees 165
Plant Area 459,000
ft2
Annual Production 49,000
thousand feet
Production Hrs. Annual 7,200
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $469,077 11,283,000
kWh
Electricity Demand $268,453 26,040
kW-mo/yr
Electricity Fees $940 -
Natural Gas $1,107,871 233,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $123,829 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $89,196

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2444: Use hot process fluids to preheat incoming process fluids $52,036 $15,000 - - $52,036
-
MMBtu
- - -
02 2.1212: Operate boilers on high fire setting $17,607 $1,000 - - $17,607
-
MMBtu
- - -
03 2.2414: Use waste heat from hot flue gases to preheat $11,043 - - - $11,043
-
MMBtu
- - -
04 2.1243: Use heat from boiler blowdown to preheat boiler feed water $10,670 $35,000 - - $10,270
-
MMBtu
$400
-
Tgal
- -
05 2.2511: Insulate bare equipment $3,164 $1,617 - - $3,164
-
MMBtu
- - -
06 2.2136: Install / repair insulation on steam lines $1,539 $1,165 - - $1,539
-
MMBtu
- - -
07 2.2135: Repair and eliminate steam leaks $1,306 $1,750 - - $1,306
-
MMBtu
- - -
08 2.3132: Recharge batteries on during off-peak demand periods $5,104 $200 $2,793
-
kWh
$2,311
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $8,448 $18,119 $6,134
147,449
kWh
$2,224
-
kW-mo/yr
- - - $90
10 2.7142: Utilize higher efficiency lamps and/or ballasts $3,040 $12,800 $2,232
53,654
kWh
$808
-
kW-mo/yr
- - - -
11 2.7135: Install occupancy sensors $3,113 $3,202 $3,113
74,833
kWh
- - - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $2,194 $451 $729
17,528
kWh
$217
-
kW-mo/yr
- - - $1,248
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,510 $100 $2,459
59,112
kWh
$891
-
kW-mo/yr
- - $(-600.0) $(-240.0)
14 2.4151: Develop a repair/replace policy $2,055 $4,256 $1,509
36,266
kWh
$546
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $123,829 $94,660 $18,969
388,842
kWh
$6,997
-
kW-mo/yr
$96,965
-
MMBtu
$400
-
Tgal
$(-600.0) $1,098
TOTAL IMPLEMENTED $89,196 $53,476 $13,063
314,009
kWh
$4,686
-
kW-mo/yr
$70,949
-
MMBtu
- $(-600.0) $1,098
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs