| Assessment Year | 2013 |
|---|---|
| Principal Product | HEPA filters |
| NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 500 |
| Plant Area |
200,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $394,998 | 6,250,650 |
kWh
|
$0.063 |
| Electricity Demand | $78,262 | 16,446 |
kW-mo/yr
|
$4.76 |
| Electricity Fees | $4,492 | - |
|
- |
| Natural Gas | $95,130 | 12,323 |
MMBtu
|
$7.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,465 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,640 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,740 | $70,400 |
$7,167
113,400
kWh
|
$12,120
-
kW-mo/yr
|
$(-3,547.0)
-
MMBtu
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,761 | $100 |
$1,697
26,856
kWh
|
$904
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | |
| 03 | 2.2437: Recover waste heat from equipment | $1,793 | $2,250 | - | - |
$1,793
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,827 | $11,647 |
$3,149
49,831
kWh
|
$1,678
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7135: Install occupancy sensors | $13,386 | $2,785 |
$13,386
211,805
kWh
|
- | - | - | - | |
| 06 | 2.7134: Use photocell controls | $2,032 | $120 |
$543
8,596
kWh
|
$1,489
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $2,053 | $513 |
$1,103
17,454
kWh
|
$759
-
kW-mo/yr
|
- | - | $191 | |
| 08 | 2.4151: Develop a repair/replace policy | $3,513 | $4,256 |
$2,292
36,266
kWh
|
$1,221
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $360 | $650 |
$328
5,184
kWh
|
$32
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $45,465 | $92,721 |
$29,665
469,392
kWh
|
$18,203
-
kW-mo/yr
|
$(-1,754.0)
-
MMBtu
|
$(-600.0) | $(-49.0) | ||
| TOTAL IMPLEMENTED | $41,640 | $90,351 |
$29,122
460,796
kWh
|
$16,714
-
kW-mo/yr
|
$(-3,547.0)
-
MMBtu
|
$(-600.0) | $(-49.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs