ITAC Assessment: NC0497
ITAC logo
ITAC Assessment: NC0497
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product HEPA filters
NAICS 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 500
Plant Area 200,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $394,998 6,250,650
kWh
Electricity Demand $78,262 16,446
kW-mo/yr
Electricity Fees $4,492 -
Natural Gas $95,130 12,323
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,465 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,640

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $15,740 $70,400 $7,167
113,400
kWh
$12,120
-
kW-mo/yr
$(-3,547.0)
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,761 $100 $1,697
26,856
kWh
$904
-
kW-mo/yr
- $(-600.0) $(-240.0)
03 2.2437: Recover waste heat from equipment $1,793 $2,250 - - $1,793
-
MMBtu
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,827 $11,647 $3,149
49,831
kWh
$1,678
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $13,386 $2,785 $13,386
211,805
kWh
- - - -
06 2.7134: Use photocell controls $2,032 $120 $543
8,596
kWh
$1,489
-
kW-mo/yr
- - -
07 2.7111: Reduce illumination to minimum necessary levels $2,053 $513 $1,103
17,454
kWh
$759
-
kW-mo/yr
- - $191
08 2.4151: Develop a repair/replace policy $3,513 $4,256 $2,292
36,266
kWh
$1,221
-
kW-mo/yr
- - -
09 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $360 $650 $328
5,184
kWh
$32
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $45,465 $92,721 $29,665
469,392
kWh
$18,203
-
kW-mo/yr
$(-1,754.0)
-
MMBtu
$(-600.0) $(-49.0)
TOTAL IMPLEMENTED $41,640 $90,351 $29,122
460,796
kWh
$16,714
-
kW-mo/yr
$(-3,547.0)
-
MMBtu
$(-600.0) $(-49.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs