Assessment Year | 2013 |
---|---|
Principal Product | Specialty chemicals |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
30,000
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $617,046 | 8,261,084 |
kWh
|
$0.075 |
Electricity Demand | $97,662 | 16,503 |
kW-mo/yr
|
$5.92 |
Electricity Fees | $4,425 | - |
|
- |
Natural Gas | $596,339 | 133,650 |
MMBtu
|
$4.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,015 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,634 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,689 | $7,449 |
$3,509
46,980
kWh
|
$417
-
kW-mo/yr
|
- | - | $763 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,248 | $4,989 |
$1,121
15,011
kWh
|
$127
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $213 | $381 |
$147
1,971
kWh
|
$16
-
kW-mo/yr
|
- | - | $50 | |
04 | 2.7135: Install occupancy sensors | $2,692 | $1,922 |
$2,692
36,034
kWh
|
- | - | - | - | |
05 | 2.2622: Replace existing chiller with high efficiency model | $15,690 | $65,000 |
$11,713
156,800
kWh
|
$3,977
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $633 | $50 |
$1,053
14,099
kWh
|
$120
-
kW-mo/yr
|
- | $(-300.0) | $(-240.0) | |
07 | 2.4151: Develop a repair/replace policy | $1,508 | $1,217 |
$1,355
18,133
kWh
|
$153
-
kW-mo/yr
|
- | - | - | |
08 | 2.2113: Repair or replace steam traps | $3,207 | $5,500 | - | - |
$5,947
-
MMBtu
|
$(-340.0) | $(-2,400.0) | |
09 | 2.2136: Install / repair insulation on steam lines | $2,135 | $2,192 | - | - |
$2,135
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $32,015 | $88,700 |
$21,590
289,028
kWh
|
$4,810
-
kW-mo/yr
|
$8,082
-
MMBtu
|
$(-640.0) | $(-1,827.0) | ||
TOTAL IMPLEMENTED | $24,634 | $79,329 |
$15,389
206,014
kWh
|
$4,393
-
kW-mo/yr
|
$8,082
-
MMBtu
|
$(-640.0) | $(-2,590.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs