Assessment Year | 2013 |
---|---|
Principal Product | Fiberglass boats |
NAICS | 336612: Boat Building |
SIC | 3732: Boat Building and Repairing |
Sales Range | $100 M to 500M |
# of Employees | 280 |
Plant Area |
355,000
ft2
|
Annual Production | 20
pieces
|
Production Hrs. Annual | 2,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $367,920 | 7,200,000 |
kWh
|
$0.051 |
Electricity Demand | $100,434 | 23,006 |
kW-mo/yr
|
$4.37 |
Electricity Fees | $89,102 | - |
|
- |
Natural Gas | $120,910 | 21,887 |
MMBtu
|
$5.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $711,192 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $704,314 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $6,129 | $5,000 |
$5,126
100,320
kWh
|
$1,003
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $435 | $100 |
$615
12,031
kWh
|
$240
-
kW-mo/yr
|
- | $(-300.0) | $(-120.0) | |
03 | 2.2437: Recover waste heat from equipment | $1,322 | $2,500 | - | - |
$1,322
-
MMBtu
|
- | - | |
04 | 2.7135: Install occupancy sensors | $9,719 | $3,000 |
$9,719
190,186
kWh
|
- | - | - | - | |
05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $5,556 | $7,000 |
$1,053
20,600
kWh
|
$1,296
-
kW-mo/yr
|
$3,207
-
MMBtu
|
- | - | |
06 | 4.452: Eliminate shift | $688,031 | $25,000 |
$13,031
255,000
kWh
|
- | - | $675,000 | - | |
TOTAL RECOMMENDED | $711,192 | $42,600 |
$29,544
578,137
kWh
|
$2,539
-
kW-mo/yr
|
$4,529
-
MMBtu
|
$674,700 | $(-120.0) | ||
TOTAL IMPLEMENTED | $704,314 | $33,100 |
$28,491
557,537
kWh
|
$1,243
-
kW-mo/yr
|
- | $674,700 | $(-120.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs