Assessment Year | 2012 |
---|---|
Principal Product | Cycling components |
NAICS | 336991: Motorcycle, Bicycle, and Parts Manufacturing |
SIC | 3751: Motorcycles, Bicycles, and Parts |
Sales Range | $5 M to 10M |
# of Employees | 35 |
Plant Area |
28,000
ft2
|
Annual Production | 15,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $16,151 | 311,100 |
kWh
|
$0.052 |
Electricity Demand | $8,204 | 960 |
kW-mo/yr
|
$8.55 |
Electricity Fees | $2,200 | - |
|
- |
Natural Gas | $3,672 | 474 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,704 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,775 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,563 | $16,950 |
$1,848
35,599
kWh
|
$1,715
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $845 | $1,125 |
$845
16,270
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $84 | $200 |
$32
610
kWh
|
$30
-
kW-mo/yr
|
$22 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $188 | $50 |
$154
2,970
kWh
|
$34
-
kW-mo/yr
|
- | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $24 | - |
$24
462
kWh
|
- | - | |
TOTAL RECOMMENDED | $4,704 | $18,325 |
$2,903
55,911
kWh
|
$1,779
-
kW-mo/yr
|
$22 | ||
TOTAL IMPLEMENTED | $3,775 | $17,000 |
$2,026
39,031
kWh
|
$1,749
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs