| Assessment Year | 2013 |
|---|---|
| Principal Product | railroad tank cars |
| NAICS | 336510: Railroad Rolling Stock Manufacturing |
| SIC | 3743: Railroad Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 511 |
| Plant Area |
360,000
ft2
|
| Annual Production | 3,000
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,087,881 | 22,353,940 |
kWh
|
$0.049 |
| Electricity Demand | $497,884 | 53,489 |
kW-mo/yr
|
$9.31 |
| Natural Gas | $402,089 | 250,810 |
MMBtu
|
$1.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $202,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $137,985 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $56,550 | $18,200 |
$39,554
791,073
kWh
|
$16,996
-
kW-mo/yr
|
- | |
| 02 | 2.2442: Preheat combustion air with waste heat | $31,447 | $13,600 | - | - |
$31,447
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,082 | $1,800 |
$1,443
28,852
kWh
|
$639
-
kW-mo/yr
|
- | |
| 04 | 2.4112: Install soft-start to eliminate nuisance trips | $1,563 | $760 | - |
$1,563
-
kW-mo/yr
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $20,763 | $63,637 |
$14,535
290,692
kWh
|
$6,228
-
kW-mo/yr
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $156 | - |
$156
3,128
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $47,580 | $267,500 |
$33,280
665,600
kWh
|
$14,300
-
kW-mo/yr
|
- | |
| 08 | 2.7135: Install occupancy sensors | $998 | $190 |
$998
19,968
kWh
|
- | - | |
| 09 | 2.2424: Use heat in flue gases to preheat products or materials | $31,162 | $150,000 | - | - |
$31,162
-
MMBtu
|
|
| 10 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $1,959 | $600 |
$1,959
39,175
kWh
|
- | - | |
| 11 | 2.4322: Use or replace with energy efficient substitutes | $8,450 | - |
$8,450
169,000
kWh
|
- | - | |
| TOTAL RECOMMENDED | $202,709 | $516,287 |
$100,374
2,007,487
kWh
|
$39,726
-
kW-mo/yr
|
$62,609
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $137,985 | $352,087 |
$98,259
1,965,185
kWh
|
$39,726
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs