ITAC Assessment: NC0449
ITAC logo
ITAC Assessment: NC0449
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Ovens and ranges
NAICS 335210: Small Electrical Appliance Manufacturing
SIC 3634: Electric Housewares and Fans
Sales Range $100
M
to 500
M
# of Employees 664
Plant Area 800,000
ft2
Annual Production 600,000
pieces
Production Hrs. Annual 3,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $949,163 18,641,100
kWh
Electricity Demand $587,103 60,394
kW-mo/yr
Natural Gas $216,499 32,705
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,115 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,183

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $39,096 $50,000 $19,716
377,555
kWh
$19,380
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $883 $1,560 $535
10,243
kWh
$348
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,300 $10,168 $1,826
36,640
kWh
$1,474
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $7,288 $37,820 - - $7,288
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,027 $6,500 $530
10,150
kWh
$497
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $1,521 $3,200 $799
15,302
kWh
$722
-
kW-mo/yr
-
TOTAL RECOMMENDED $53,115 $109,248 $23,406
449,890
kWh
$22,421
-
kW-mo/yr
$7,288
-
MMBtu
TOTAL IMPLEMENTED $4,183 $11,728 $2,361
46,883
kWh
$1,822
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs