ITAC Assessment: NC0438
ITAC logo
ITAC Assessment: NC0438
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Pharmceutical Rubber
NAICS 325212: Synthetic Rubber Manufacturing
SIC 2822: Synthetic Rubber (Vulcanizable Elastomers)
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 172,682
ft2
Annual Production 4,000,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,036,858 15,187,614
kWh
Electricity Demand $217,855 9,505
kW-mo/yr
Electricity Fees $84,356 -
Natural Gas $564,948 86,494
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $162,602 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,612

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1392: Replace purchased steam with other energy source $62,448 $94,000 - - $143,448
-
MMBtu
$(-81,000.0)
-
MMBtu
- - -
02 2.1243: Use heat from boiler blowdown to preheat boiler feed water $8,972 $7,800 - - $8,972
-
MMBtu
- - - -
03 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $19,068 $32,000 $18,335
268,560
kWh
$12,307
-
kW-mo/yr
$(-11,574.0)
-
MMBtu
- - - -
04 2.2113: Repair or replace steam traps $19,936 $5,500 - - $23,116
-
MMBtu
- - $(-300.0) $(-2,880.0)
05 3.4141: Replace the chlorination stage with an oxygen or ozone stage $43,023 $92,800 $(-1,081.0)
(-15,840)
kWh
$(-1,816.0)
-
kW-mo/yr
- - $25,920
-
Tgal
- $20,000
06 2.4151: Develop a repair/replace policy $5,515 $5,548 $3,300
48,331
kWh
$2,215
-
kW-mo/yr
- - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,224 $300 $1,833
26,856
kWh
$1,231
-
kW-mo/yr
- - - $(-600.0) $(-240.0)
08 2.7135: Install occupancy sensors $1,416 $2,112 $1,416
20,736
kWh
- - - - - -
TOTAL RECOMMENDED $162,602 $240,060 $23,803
348,643
kWh
$13,937
-
kW-mo/yr
$163,962
-
MMBtu
$(-81,000.0)
-
MMBtu
$25,920
-
Tgal
$(-900.0) $16,880
TOTAL IMPLEMENTED $12,612 $10,212 $3,249
47,592
kWh
$1,231
-
kW-mo/yr
$8,972
-
MMBtu
- - $(-600.0) $(-240.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs