ITAC Assessment: NC0436
ITAC logo
ITAC Assessment: NC0436
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Aircraft structures and military enclosures
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 929,000
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $760,807 26,037,220
kWh
Electricity Demand $675,970 52,118
kW-mo/yr
Natural Gas $852,442 150,499
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $215,647 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,599

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $107,275 $300,044 $56,510
1,933,963
kWh
$52,306
-
kW-mo/yr
- - $(-1,541.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,241 $21,888 $6,154
210,593
kWh
$4,087
-
kW-mo/yr
- - -
03 2.4226: Use / purchase optimum sized compressor $18,076 $4,000 $11,228
384,255
kWh
$6,848
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,560 $100 $5,442
186,246
kWh
$3,318
-
kW-mo/yr
- $(-960.0) $(-240.0)
05 2.7224: Reduce space conditioning during non-working hours $8,955 $11,000 $8,434
288,634
kWh
- $521
-
MMBtu
- -
06 2.2136: Install / repair insulation on steam lines $12,954 $6,435 - - $12,954
-
MMBtu
- -
07 2.1243: Use heat from boiler blowdown to preheat boiler feed water $5,967 $27,000 - - $5,967
-
MMBtu
- -
08 2.1233: Analyze flue gas for proper air/fuel ratio $3,009 $1,000 - - $3,009
-
MMBtu
- -
09 2.2514: Cover open tanks $1,610 $5,000 - - $1,610
-
MMBtu
- -
10 2.4322: Use or replace with energy efficient substitutes $40,000 $10,000 - - - - $40,000
TOTAL RECOMMENDED $215,647 $386,467 $87,768
3,003,691
kWh
$66,559
-
kW-mo/yr
$24,061
-
MMBtu
$(-960.0) $38,219
TOTAL IMPLEMENTED $41,599 $11,535 $16,670
570,501
kWh
$10,166
-
kW-mo/yr
$15,963
-
MMBtu
$(-960.0) $(-240.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs