ITAC Assessment: NC0422
ITAC logo
ITAC Assessment: NC0422
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Gas dispensers
NAICS 333913: Measuring and Dispensing Pump Manufacturing
SIC 3586: Measuring and Dispensing Pumps
Sales Range $100
M
to 500
M
# of Employees 1,100
Plant Area 885,000
ft2
Annual Production 25,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $850,650 17,352,000
kWh
Electricity Demand $183,072 40,206
kW-mo/yr
Electricity Fees $36 -
Natural Gas $319,758 55,184
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $97,949 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.1133: Adjust burners for efficient operation $3,623 $1,000 - - $3,623
-
MMBtu
- - -
02 2.1224: Replace boiler $17,336 $37,000 - - $17,336
-
MMBtu
- - -
03 2.2121: Increase amount of condensate returned $15,021 $10,000 - - $8,429
-
MMBtu
- - $6,592
-
Tgal
04 2.2136: Install / repair insulation on steam lines $3,316 $1,618 - - $3,316
-
MMBtu
- - -
05 2.2414: Use waste heat from hot flue gases to preheat $8,982 $38,000 - - $8,982
-
MMBtu
- - -
06 2.2514: Cover open tanks $11,237 $15,000 $8,966
244,360
kWh
$2,271
-
kW-mo/yr
- - - -
07 2.4224: Upgrade controls on compressors $15,795 $1,500 $15,795
506,225
kWh
- - - - -
08 2.2437: Recover waste heat from equipment $10,815 $22,930 - - $10,815
-
MMBtu
- - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $6,211 $100 $4,745
129,322
kWh
$1,466
-
kW-mo/yr
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,027 $100 $2,374
64,696
kWh
$733
-
kW-mo/yr
- $(-600.0) $(-480.0) -
11 2.8123: Pay utility bills on time $3,586 - $3,586
-
kWh
- - - - -
TOTAL RECOMMENDED $97,949 $127,248 $35,466
944,603
kWh
$4,470
-
kW-mo/yr
$52,501
-
MMBtu
$(-600.0) $(-480.0) $6,592
-
Tgal
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs