| Assessment Year | 2010 |
|---|---|
| Principal Product | Lightweight aggregate |
| NAICS | 327992: Ground or Treated Mineral and Earth Manufacturing |
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $5 M to 10M |
| # of Employees | 27 |
| Plant Area |
11,933
ft2
|
| Annual Production | 950,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,753 | 1,366,441 |
kWh
|
$0.069 |
| Electricity Demand | $67,727 | 20,900 |
kW-mo/yr
|
$3.24 |
| Fuel Oil #4 | $6,020 | 602 |
MMBtu
|
$10.00 |
| Other Energy | $800,000 | 352,000 |
MMBtu
|
$2.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $105,713 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $101,033 | $272,411 |
$95,920
1,747,200
kWh
|
$5,113
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,826 | $100 |
$2,683
48,878
kWh
|
$143
-
kW-mo/yr
|
- | - | |
| 03 | 2.4151: Develop a repair/replace policy | $569 | $580 |
$540
9,833
kWh
|
$29
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,167 | $3,040 |
$1,278
23,280
kWh
|
$68
-
kW-mo/yr
|
$(-255.0) | $76 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $118 | $435 |
$104
1,893
kWh
|
$14
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $105,713 | $276,566 |
$100,525
1,831,084
kWh
|
$5,367
-
kW-mo/yr
|
$(-255.0) | $76 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs