Assessment Year | 2010 |
---|---|
Principal Product | Wood flooring |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
300,000
ft2
|
Annual Production | 33,000
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $616,141 | 10,502,400 |
kWh
|
$0.059 |
Electricity Demand | $375,636 | 31,687 |
kW-mo/yr
|
$11.85 |
Natural Gas | $196,886 | 19,157 |
MMBtu
|
$10.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $784,712 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $773,579 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,189 | $1,000 | - | - |
$4,189
-
MMBtu
|
- | - | - | |
02 | 2.2136: Install / repair insulation on steam lines | $5,644 | $1,689 | - | - |
$5,644
-
MMBtu
|
- | - | - | |
03 | 2.2113: Repair or replace steam traps | $5,428 | $5,500 | - | - |
$7,053
-
MMBtu
|
$(-225.0) | $(-1,400.0) | - | |
04 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $712,007 | $1,750,000 |
$436,153
7,434,000
kWh
|
$122,130
-
kW-mo/yr
|
$179,458
-
MMBtu
|
- | - |
$(-25,734.0)
-
Tgal
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,000 | $7,665 |
$2,626
44,760
kWh
|
$734
-
kW-mo/yr
|
- | - | $(-360.0) | - | |
06 | 2.7135: Install occupancy sensors | $27,873 | $53,873 |
$25,480
434,296
kWh
|
$4,687
-
kW-mo/yr
|
- | $(-3,121.0) | $827 | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,195 | $2,876 |
$1,717
29,268
kWh
|
$478
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $882 | $924 |
$882
15,029
kWh
|
- | - | - | - | - | |
09 | 2.3212: Optimize plant power factor | $11,133 | $20,000 | - |
$11,133
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4151: Develop a repair/replace policy | $11,081 | $2,538 |
$10,582
180,370
kWh
|
$499
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,280 | $100 |
$2,120
28,264
kWh
|
- | - | $(-600.0) | $(-240.0) | - | |
TOTAL RECOMMENDED | $784,712 | $1,846,165 |
$479,560
8,165,987
kWh
|
$139,661
-
kW-mo/yr
|
$196,344
-
MMBtu
|
$(-3,946.0) | $(-1,173.0) |
$(-25,734.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $773,579 | $1,826,165 |
$479,560
8,165,987
kWh
|
$128,528
-
kW-mo/yr
|
$196,344
-
MMBtu
|
$(-3,946.0) | $(-1,173.0) |
$(-25,734.0)
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs