Assessment Year | 2010 |
---|---|
Principal Product | Paints and stains |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $50 M to 100M |
# of Employees | 59 |
Plant Area |
70,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,990 | 617,200 |
kWh
|
$0.045 |
Electricity Demand | $9,629 | 1,754 |
kW-mo/yr
|
$5.49 |
Natural Gas | $52,788 | 4,290 |
MMBtu
|
$12.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,644 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,127 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $227 | $200 |
$634
12,085
kWh
|
$133
-
kW-mo/yr
|
- | $(-300.0) | $(-240.0) | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $900 | $100 |
$747
14,248
kWh
|
$153
-
kW-mo/yr
|
- | - | - | |
03 | 2.4151: Develop a repair/replace policy | $1,096 | $4,858 |
$834
15,902
kWh
|
$262
-
kW-mo/yr
|
- | - | - | |
04 | 3.5142: Treat and reuse equipment cleaning solutions | $31,421 | - |
$(-9,146.0)
(-174,400)
kWh
|
$(-2,872.0)
-
kW-mo/yr
|
$43,439
-
gal
|
- | - | |
TOTAL RECOMMENDED | $33,644 | $5,158 |
$(-6,931.0)
(-132,165)
kWh
|
$(-2,324.0)
-
kW-mo/yr
|
$43,439
-
gal
|
$(-300.0) | $(-240.0) | ||
TOTAL IMPLEMENTED | $1,127 | $300 |
$1,381
26,333
kWh
|
$286
-
kW-mo/yr
|
- | $(-300.0) | $(-240.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs