| Assessment Year | 2010 |
|---|---|
| Principal Product | Food Flavorings |
| NAICS | 311930: Flavoring Syrup and Concentrate Manufacturing |
| SIC | 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
33,000
ft2
|
| Annual Production | 6,800,000
lb
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $43,498 | 1,200,560 |
kWh
|
$0.036 |
| Electricity Demand | $18,363 | 2,650 |
kW-mo/yr
|
$6.93 |
| Electricity Fees | $2,714 | - |
|
- |
| Natural Gas | $45,097 | 3,614 |
MMBtu
|
$12.48 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,596 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,556 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $9,787 | - | - | - |
$10,287
-
MMBtu
|
$(-500.0) | - | |
| 02 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $3,632 | $14,000 | - | - |
$3,632
-
MMBtu
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $497 | $100 |
$528
16,114
kWh
|
$329
-
kW-mo/yr
|
- | $(-300.0) | $(-60.0) | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,982 | - |
$2,164
66,067
kWh
|
$1,347
-
kW-mo/yr
|
- | $(-723.0) | $194 | |
| 05 | 2.4151: Develop a repair/replace policy | $445 | $1,454 |
$274
8,364
kWh
|
$171
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2514: Cover open tanks | $3,253 | - |
$183
5,433
kWh
|
$112
-
kW-mo/yr
|
$2,958
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $20,596 | $15,554 |
$3,149
95,978
kWh
|
$1,959
-
kW-mo/yr
|
$16,877
-
MMBtu
|
$(-1,523.0) | $134 | ||
| TOTAL IMPLEMENTED | $7,556 | $15,554 |
$2,966
90,545
kWh
|
$1,847
-
kW-mo/yr
|
$3,632
-
MMBtu
|
$(-1,023.0) | $134 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs