Assessment Year | 2009 |
---|---|
Principal Product | Printing sleeves |
NAICS | 333244: Printing Machinery and Equipment Manufacturing |
SIC | 3555: Printing Trades Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
88,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,281 | 6,846,331 |
kWh
|
$0.033 |
Electricity Demand | $131,821 | 15,067 |
kW-mo/yr
|
$8.75 |
Electricity Fees | $7,851 | - |
|
- |
Natural Gas | $60,725 | 4,490 |
MMBtu
|
$13.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,509 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $958 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,752 | $54,282 |
$17,343
379,320
kWh
|
$2,178
-
kW-mo/yr
|
- | $(-3,379.0) | $610 | |
02 | 2.2437: Recover waste heat from equipment | $3,172 | $4,300 | - | - |
$3,172
-
MMBtu
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $627 | - |
$557
12,180
kWh
|
$70
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $387 | $100 |
$859
18,787
kWh
|
$108
-
kW-mo/yr
|
- | $(-400.0) | $(-180.0) | |
05 | 2.4151: Develop a repair/replace policy | $571 | $892 |
$507
11,079
kWh
|
$64
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $21,509 | $59,574 |
$19,266
421,366
kWh
|
$2,420
-
kW-mo/yr
|
$3,172
-
MMBtu
|
$(-3,779.0) | $430 | ||
TOTAL IMPLEMENTED | $958 | $992 |
$1,366
29,866
kWh
|
$172
-
kW-mo/yr
|
- | $(-400.0) | $(-180.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs