ITAC Assessment: NC0383
ITAC logo
ITAC Assessment: NC0383
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Specialty chemicals
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 116
Plant Area 300,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $554,374 12,526,240
kWh
Electricity Demand $228,551 23,086
kW-mo/yr
Electricity Fees $1,837 -
Natural Gas $926,701 107,361
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $154,206 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $117,183

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.1231: Establish burner maintenance schedule for boilers $16,582 $1,000 - - $16,582
-
MMBtu
- - -
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $38,474 - - - $18,474
-
MMBtu
- - $20,000
03 2.2414: Use waste heat from hot flue gases to preheat $42,558 $50,000 - - $42,558
-
MMBtu
- - -
04 2.2121: Increase amount of condensate returned $19,037 $30,000 - - $19,037
-
MMBtu
- - -
05 2.2124: Install de-aerator in place of condensate tank $4,551 $10,000 - - $4,551
-
MMBtu
- - -
06 2.2628: Utilize a less expensive cooling method $4,245 $20,000 $3,235
73,100
kWh
$1,010
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,848 $50 $1,408
31,820
kWh
$440
-
kW-mo/yr
- - - -
08 2.2437: Recover waste heat from equipment $11,043 $6,150 - - $11,043
-
MMBtu
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,623 $100 $1,923
43,443
kWh
$600
-
kW-mo/yr
- $(-600.0) $(-300.0) -
10 2.4151: Develop a repair/replace policy $11,700 $11,589 $8,916
201,468
kWh
$2,784
-
kW-mo/yr
- - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $1,695 $1,497 $1,297
29,298
kWh
$398
-
kW-mo/yr
- - - -
12 2.7121: Utilize daylight whenever possible in lieu of artificial light $850 $750 $560
12,654
kWh
$290
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $154,206 $131,136 $17,339
391,783
kWh
$5,522
-
kW-mo/yr
$112,245
-
MMBtu
$(-600.0) $(-300.0) $20,000
TOTAL IMPLEMENTED $117,183 $74,186 $12,136
274,209
kWh
$3,782
-
kW-mo/yr
$82,165
-
MMBtu
$(-600.0) $(-300.0) $20,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs