ITAC Assessment: NC0382
ITAC logo
ITAC Assessment: NC0382
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Paints
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 300,000
ft2
Annual Production 6,000
Tgal
Production Hrs. Annual 8,600
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $234,133 76,860,000
kWh
Electricity Demand $136,614 14,376
kW-mo/yr
Electricity Fees $9,515 -
Natural Gas $201,166 17,445
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,986 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,817

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 2.133: Alternate fuel $1,350 $1,000 - - $1,350
-
MMBtu
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,305 $8,000 $812
-
kWh
$7,493
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $11,864 $6,150 - - $11,864
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,333 $100 $2,333
76,987
kWh
$900
-
kW-mo/yr
- $(-600.0) $(-300.0)
05 2.3132: Recharge batteries on during off-peak demand periods $1,226 - $262
-
kWh
$964
-
kW-mo/yr
- - -
06 2.4151: Develop a repair/replace policy $1,644 $2,483 $1,187
39,148
kWh
$457
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,264 $4,408 $906
30,100
kWh
$358
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $27,986 $22,141 $5,500
146,235
kWh
$10,172
-
kW-mo/yr
$13,214
-
MMBtu
$(-600.0) $(-300.0)
TOTAL IMPLEMENTED $7,817 $7,991 $4,688
146,235
kWh
$2,679
-
kW-mo/yr
$1,350
-
MMBtu
$(-600.0) $(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs