Assessment Year | 2008 |
---|---|
Principal Product | Rolls for paper industry |
NAICS | 333243: Sawmill, Woodworking, and Paper Machinery Manufacturing |
SIC | 3554: Paper Industries Machinery |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
60,000
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $93,372 | 3,585,727 |
kWh
|
$0.026 |
Electricity Demand | $55,480 | 7,447 |
kW-mo/yr
|
$7.45 |
Electricity Fees | $11,381 | - |
|
- |
Natural Gas | $160,469 | 12,787 |
MMBtu
|
$12.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,635 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,929 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $871 | $800 | - | - |
$871
-
MMBtu
|
- | - | |
02 | 2.2126: Lower operating pressure of condenser (steam) | $333 | $100 | - | - |
$333
-
MMBtu
|
- | - | |
03 | 2.7314: Reduce ventilation air | $7,706 | $25,500 | - | - |
$7,706
-
MMBtu
|
- | - | |
04 | 2.7313: Recycle air for heating, ventilation and air conditioning | $2,284 | $3,000 | - | - |
$2,284
-
MMBtu
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $237 | $50 |
$151
5,782
kWh
|
$86
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $269 | $100 |
$835
32,078
kWh
|
$334
-
kW-mo/yr
|
- | $(-600.0) | $(-300.0) | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $101 | $308 |
$64
2,472
kWh
|
$37
-
kW-mo/yr
|
- | - | - | |
08 | 2.4151: Develop a repair/replace policy | $834 | $1,728 |
$532
20,446
kWh
|
$302
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $12,635 | $31,586 |
$1,582
60,778
kWh
|
$759
-
kW-mo/yr
|
$11,194
-
MMBtu
|
$(-600.0) | $(-300.0) | ||
TOTAL IMPLEMENTED | $4,929 | $6,086 |
$1,582
60,778
kWh
|
$759
-
kW-mo/yr
|
$3,488
-
MMBtu
|
$(-600.0) | $(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs