Assessment Year | 2000 |
---|---|
Principal Product | Plastic Molding |
NAICS |
n/a
|
SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
Sales Range | $50 M to 100M |
# of Employees | 214 |
Plant Area |
n/a
|
Annual Production | 80,000,000
pieces
|
Production Hrs. Annual | 8,544
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $234,309 | 6,354,045 |
kWh
|
$0.037 |
Electricity Demand | $93,484 | 13,962 |
kW-mo/yr
|
$6.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,098 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,107 | $850 | n/a |
$4,417
141,266
kWh
|
$1,690
-
kW-mo/yr
|
- |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,419 | $1,771 | n/a |
$2,599
82,943
kWh
|
$820
-
kW-mo/yr
|
- |
03 | 2.7135: Install occupancy sensors | $2,151 | $1,175 | n/a |
$2,151
68,581
kWh
|
- | - |
04 | 2.8112: Combine utility meters | $1,560 | - | n/a | - | - | $1,560 |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $562 | $1,492 | n/a |
$411
12,016
kWh
|
$151
-
kW-mo/yr
|
- |
06 | 2.7144: Install spectral reflectors / delamp | $181 | $67 | n/a | - |
$181
-
kW-mo/yr
|
- |
07 | 2.7131: Add area lighting switches | $118 | - | n/a |
$118
2,345
kWh
|
- | - |
TOTAL RECOMMENDED | $14,098 | $5,355 |
$9,696
307,151
kWh
|
$2,842
-
kW-mo/yr
|
$1,560 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs