Assessment Year | 2007 |
---|---|
Principal Product | Paints, stains, and varnishs |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
200,000
ft2
|
Annual Production | 12,000
Tgal
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $190,669 | 4,539,750 |
kWh
|
$0.042 |
Electricity Demand | $76,066 | 17,898 |
kW-mo/yr
|
$4.25 |
Electricity Fees | $6,568 | - |
|
- |
Natural Gas | $190,148 | 13,207 |
MMBtu
|
$14.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,061 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,688 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,209 | $1,540 |
$3,049
72,600
kWh
|
$617
-
kW-mo/yr
|
- | - | - | $2,543 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,791 | $1,674 |
$1,437
34,208
kWh
|
$354
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $6,894 | $19,950 | - | - |
$6,894
-
MMBtu
|
- | - | - | |
04 | 2.4151: Develop a repair/replace policy | $658 | $617 |
$546
12,988
kWh
|
$112
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $579 | $100 |
$1,477
35,160
kWh
|
$302
-
kW-mo/yr
|
- | - | $(-900.0) | $(-300.0) | |
06 | 2.1133: Adjust burners for efficient operation | $1,849 | $1,200 | - | - |
$1,849
-
MMBtu
|
- | - | - | |
07 | 2.1133: Adjust burners for efficient operation | $1,150 | $1,200 | - | - |
$1,150
-
MMBtu
|
- | - | - | |
08 | 2.1133: Adjust burners for efficient operation | $452 | $500 | - | - |
$452
-
MMBtu
|
- | - | - | |
09 | 2.1232: Keep boiler tubes clean | $1,550 | $2,395 | - | - |
$1,150
-
MMBtu
|
- | - | $400 | |
10 | 2.1241: Reduce excessive boiler blowdown | $553 | - | - | - |
$553
-
MMBtu
|
- | - | - | |
11 | 2.2121: Increase amount of condensate returned | $376 | $1,000 | - | - |
$116
-
MMBtu
|
$10
-
Tgal
|
- | $250 | |
TOTAL RECOMMENDED | $22,061 | $30,176 |
$6,509
154,956
kWh
|
$1,385
-
kW-mo/yr
|
$12,164
-
MMBtu
|
$10
-
Tgal
|
$(-900.0) | $2,893 | ||
TOTAL IMPLEMENTED | $12,688 | $6,831 |
$6,509
154,956
kWh
|
$1,385
-
kW-mo/yr
|
$3,451
-
MMBtu
|
- | $(-900.0) | $2,243 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs