ITAC Assessment: WV0154
ITAC logo
ITAC Assessment: WV0154
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Rubber, plastic, bulk goods
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 100,000
ft2
Annual Production 585
ton
Production Hrs. Annual 1,920
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,751 3,633,353
kWh
Electricity Demand $120,836 13,942
kW-mo/yr
Natural Gas $385,291 132,601
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $205,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.7241: Install outside air damper / economizer on hvac unit $1,075 $2,580 $1,075
28,722
kWh
- - -
02 2.2511: Insulate bare equipment $16,667 $9,432 - $16,667
-
MMBtu
- -
03 2.2511: Insulate bare equipment $4,282 $5,130 - $4,282
-
MMBtu
- -
04 2.2136: Install / repair insulation on steam lines $322 $482 - $322
-
MMBtu
- -
05 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $162 $550 - $162
-
MMBtu
- -
06 2.7124: Make a practice of turning off lights when not needed $142 $220 $142
3,810
kWh
- - -
07 3.4115: Recover and reuse cooling water $670 $1,525 - - $670
-
Tgal
-
08 3.4116: Meter recycled water (to reduce sewer charges) $1,940 $550 - - $1,940
-
Tgal
-
09 4.521: Clear and rent existing space $180,000 $4,000 - - - $180,000
TOTAL RECOMMENDED $205,260 $24,469 $1,217
32,532
kWh
$21,433
-
MMBtu
$2,610
-
Tgal
$180,000
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs