| Assessment Year | 2007 |
|---|---|
| Principal Product | Corrugated board |
| NAICS | 322212: Folding Paperboard Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
155,000
ft2
|
| Annual Production | 480,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $161,829 | 4,903,920 |
kWh
|
$0.033 |
| Electricity Demand | $115,267 | 8,660 |
kW-mo/yr
|
$13.31 |
| Electricity Fees | $9,302 | - |
|
- |
| Natural Gas | $518,813 | 50,229 |
MMBtu
|
$10.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $93,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,506 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $20,317 | $10,000 | - | - |
$20,317
-
MMBtu
|
- | - | |
| 02 | 2.2135: Repair and eliminate steam leaks | $9,594 | $2,250 | - | - |
$9,594
-
MMBtu
|
- | - | |
| 03 | 2.7313: Recycle air for heating, ventilation and air conditioning | $35,946 | $33,785 | - | - |
$35,946
-
MMBtu
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $12,267 | - |
$12,267
371,713
kWh
|
- | - | - | - | |
| 05 | 2.4151: Develop a repair/replace policy | $1,032 | $662 |
$577
17,486
kWh
|
$455
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $12,731 | $12,000 | - | - |
$12,731
-
MMBtu
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $836 | $300 |
$1,293
39,174
kWh
|
$1,043
-
kW-mo/yr
|
- | $(-900.0) | $(-600.0) | |
| 08 | 2.7134: Use photocell controls | $761 | $750 |
$361
10,950
kWh
|
$400
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $93,484 | $59,747 |
$14,498
439,323
kWh
|
$1,898
-
kW-mo/yr
|
$78,588
-
MMBtu
|
$(-900.0) | $(-600.0) | ||
| TOTAL IMPLEMENTED | $56,506 | $25,300 |
$13,921
421,837
kWh
|
$1,443
-
kW-mo/yr
|
$42,642
-
MMBtu
|
$(-900.0) | $(-600.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs