Assessment Year | 2007 |
---|---|
Principal Product | Copper tubing |
NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
400,000
ft2
|
Annual Production | 60,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,851,981 | 44,290,334 |
kWh
|
$0.042 |
Electricity Fees | $362,232 | - |
|
- |
Natural Gas | $960,175 | 77,701 |
MMBtu
|
$12.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $822,674 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $6,682 | $13,000 |
$2,521
59,189
kWh
|
$4,161
-
MMBtu
|
- | - | - | |
02 | 2.4151: Develop a repair/replace policy | $3,860 | $2,751 |
$3,860
90,608
kWh
|
- | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $5,543 | $24,660 |
$(-187.0)
(-4,380)
kWh
|
$5,730
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $308 | $100 |
$1,508
35,400
kWh
|
- | $(-900.0) | $(-300.0) | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $327 | $316 |
$327
7,666
kWh
|
- | - | - | - | |
06 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $767 | $1,000 |
$767
18,000
kWh
|
- | - | - | - | |
07 | 2.7134: Use photocell controls | $187 | $200 |
$187
4,380
kWh
|
- | - | - | - | |
08 | 4.121: Maintain clean conditions before painting | $805,000 | $56,000 | - | - | - | - | $805,000 | |
TOTAL RECOMMENDED | $822,674 | $98,027 |
$8,983
210,863
kWh
|
$9,891
-
MMBtu
|
$(-900.0) | $(-300.0) | $805,000 | ||
TOTAL IMPLEMENTED | $635 | $416 |
$1,835
43,066
kWh
|
- | $(-900.0) | $(-300.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs