Assessment Year | 2006 |
---|---|
Principal Product | Corrugated boxes and displays |
NAICS | 322212: Folding Paperboard Box Manufacturing |
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $50 M to 100M |
# of Employees | 220 |
Plant Area |
330,000
ft2
|
Annual Production | 930,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $540,618 | 12,286,781 |
kWh
|
$0.044 |
Electricity Demand | $204,209 | 18,926 |
kW-mo/yr
|
$10.79 |
Natural Gas | $690,431 | 68,937 |
MMBtu
|
$10.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,480 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $18,045 | $2,000 | - | - |
$18,045
-
MMBtu
|
- | - | - | |
02 | 2.2162: Reduce excess steam bleeding | $23,110 | $13,525 | - | - |
$18,517
-
MMBtu
|
- | - |
$4,593
-
Tgal
|
|
03 | 2.2511: Insulate bare equipment | $3,668 | $1,000 | - | - |
$3,668
-
MMBtu
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $2,375 | $1,000 | - | - |
$2,375
-
MMBtu
|
- | - | - | |
05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $19,058 | $28,785 | - | - |
$19,058
-
MMBtu
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $6,087 | $4,340 | - | - |
$6,087
-
MMBtu
|
- | - | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $11,246 | $5,000 |
$11,246
255,600
kWh
|
- | - | - | - | - | |
08 | 3.4114: Replace city water with recycled water via cooling tower | $5,891 | $4,000 |
$(-264.0)
(-6,000)
kWh
|
$(-129.0)
-
kW-mo/yr
|
- |
$6,716
-
Tgal
|
$(-432.0) | - | |
TOTAL RECOMMENDED | $89,480 | $59,650 |
$10,982
249,600
kWh
|
$(-129.0)
-
kW-mo/yr
|
$67,750
-
MMBtu
|
$6,716
-
Tgal
|
$(-432.0) |
$4,593
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs