Assessment Year | 2006 |
---|---|
Principal Product | Corrugated packaging |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2670: |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 300,000
thousand feet
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,277 | 1,174,800 |
kWh
|
$0.040 |
Electricity Demand | $28,231 | 3,361 |
kW-mo/yr
|
$8.40 |
Electricity Fees | $3,654 | - |
|
- |
Natural Gas | $69,759 | 5,402 |
MMBtu
|
$12.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,514 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $353 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7313: Recycle air for heating, ventilation and air conditioning | $11,414 | $25,000 | - | - |
$11,414
-
MMBtu
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $9,082 | $100 |
$4,341
107,973
kWh
|
- |
$4,741
-
MMBtu
|
- | - | - | |
03 | 2.7122: Disconnect ballasts | $1,454 | $1,650 |
$955
23,760
kWh
|
$499
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4151: Develop a repair/replace policy | $1,455 | $929 |
$955
23,767
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $353 | $100 |
$452
11,238
kWh
|
$241
-
kW-mo/yr
|
- | $(-240.0) | - | $(-100.0) | |
06 | 4.625: Develop standard operating procedures | $55,756 | $2,540 | - | - | - | $7,500 | $48,256 | - | |
TOTAL RECOMMENDED | $79,514 | $30,319 |
$6,703
166,738
kWh
|
$1,240
-
kW-mo/yr
|
$16,155
-
MMBtu
|
$7,260 | $48,256 | $(-100.0) | ||
TOTAL IMPLEMENTED | $353 | $100 |
$452
11,238
kWh
|
$241
-
kW-mo/yr
|
- | $(-240.0) | - | $(-100.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs