ITAC Assessment: NC0308
ITAC logo
ITAC Assessment: NC0308
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Cartons for the food industry
NAICS 322212: Folding Paperboard Box Manufacturing
SIC 2657: Folding Paperboard Boxes, Including Sanitary
Sales Range $10
M
to 50
M
# of Employees 124
Plant Area 156,000
ft2
Annual Production 999,999,999
pieces
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $226,006 8,128,000
kWh
Electricity Demand $141,768 14,799
kW-mo/yr
Electricity Fees $12,059 -
Natural Gas $15,780 1,566
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,041 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,841

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4226: Use / purchase optimum sized compressor $9,359 $20,313 $6,307
226,800
kWh
$3,052
-
kW-mo/yr
- - -
02 2.2437: Recover waste heat from equipment $6,017 $2,450 - - $6,017
-
MMBtu
- -
03 4.211: Consider use / purchase of bulk materials where possible $15,600 $1,000 - - - - $15,600
04 2.7241: Install outside air damper / economizer on hvac unit $13,767 $6,500 $13,767
495,024
kWh
- - - -
05 4.212: Adopt in-house material generation $3,600 $4,000 - - - $3,600 -
06 2.7135: Install occupancy sensors $1,493 $2,000 $972
34,943
kWh
$521
-
kW-mo/yr
- - -
07 2.7132: Install timers on light switches in little used areas $867 $750 $629
22,630
kWh
$238
-
kW-mo/yr
- - -
08 2.7111: Reduce illumination to minimum necessary levels $338 $160 $111
4,004
kWh
$227
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $51,041 $37,173 $21,786
783,401
kWh
$4,038
-
kW-mo/yr
$6,017
-
MMBtu
$3,600 $15,600
TOTAL IMPLEMENTED $31,841 $32,173 $21,786
783,401
kWh
$4,038
-
kW-mo/yr
$6,017
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs