ITAC Assessment: NC0265
ITAC logo
ITAC Assessment: NC0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Rubber hoses and products
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 3059:
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 173,000
ft2
Annual Production 3,750,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,096 4,788,000
kWh
Electricity Demand $69,258 16,296
kW-mo/yr
Electricity Fees $8,577 -
Natural Gas $223,639 41,598
MMBtu
Fuel Oil #6 $85,827 16,807
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,811 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $55,605

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #6 Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $23,793 $7,000 - $23,177
-
kW-mo/yr
$616 - - - - -
02 3.4111: Use closed cycle process to minimize waste water production $13,226 $24,506 - - - $5,840
-
MMBtu
$2,386
-
MMBtu
$5,000
-
Tgal
- -
03 3.4111: Use closed cycle process to minimize waste water production $7,348 $3,525 - - - $3,576
-
MMBtu
- $1,417
-
Tgal
- $2,355
04 2.2437: Recover waste heat from equipment $5,206 $1,100 - - - $5,206
-
MMBtu
- - - -
05 2.1133: Adjust burners for efficient operation $7,094 $1,000 - - - $7,094
-
MMBtu
- - - -
06 2.4226: Use / purchase optimum sized compressor $2,361 - $2,361
62,664
kWh
- - - - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,469 $300 $2,082
49,561
kWh
$287
-
kW-mo/yr
- - - - $(-600.0) $(-300.0)
08 2.7124: Make a practice of turning off lights when not needed $214 $50 $214
5,112
kWh
- - - - - - -
09 2.7135: Install occupancy sensors $100 $89 $100
2,400
kWh
- - - - - - -
TOTAL RECOMMENDED $60,811 $37,570 $4,757
119,737
kWh
$23,464
-
kW-mo/yr
$616 $21,716
-
MMBtu
$2,386
-
MMBtu
$6,417
-
Tgal
$(-600.0) $2,055
TOTAL IMPLEMENTED $55,605 $36,470 $4,757
119,737
kWh
$23,464
-
kW-mo/yr
$616 $16,510
-
MMBtu
$2,386
-
MMBtu
$6,417
-
Tgal
$(-600.0) $2,055
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #6 Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs