| Assessment Year | 2002 |
|---|---|
| Principal Product | Case good furniture |
| NAICS |
n/a
|
| SIC | 2511: Wood Household Furniture, Except Upholstered |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
220,000
ft2
|
| Annual Production | 14,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $192,291 | 4,623,680 |
kWh
|
$0.042 |
| Electricity Demand | $75,600 | 21,600 |
kW-mo/yr
|
$3.50 |
| Electricity Fees | $12,436 | - |
|
- |
| Fuel Oil #2 | $8,000 | 1,400 |
MMBtu
|
$5.71 |
| Coal | $2,700 | 1,246 |
MMBtu
|
$2.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $116,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $116,127 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1232: Keep boiler tubes clean | $12,204 | $10,000 | - | - |
$8,000
-
MMBtu
|
$4,204
-
MMBtu
|
- | |
| 02 | 2.4151: Develop a repair/replace policy | $673 | $1,146 |
$447
10,741
kWh
|
$226
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7134: Use photocell controls | $118 | $200 |
$96
2,300
kWh
|
$22
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $132 | $60 |
$88
2,112
kWh
|
$44
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.8118: Check for accuracy of utility / power meters | $3,000 | $1,000 |
$1,923
46,224
kWh
|
$756
-
kW-mo/yr
|
$321
-
MMBtu
|
- | - | |
| 06 | 4.711: Initiate a total quality management program | $100,000 | $200,000 | - | - | - | - | $100,000 | |
| TOTAL RECOMMENDED | $116,127 | $212,406 |
$2,554
61,377
kWh
|
$1,048
-
kW-mo/yr
|
$8,321
-
MMBtu
|
$4,204
-
MMBtu
|
$100,000 | ||
| TOTAL IMPLEMENTED | $116,127 | $212,406 |
$2,554
61,377
kWh
|
$1,048
-
kW-mo/yr
|
$8,321
-
MMBtu
|
$4,204
-
MMBtu
|
$100,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs