ITAC Assessment: NC0234
ITAC logo
ITAC Assessment: NC0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Sockets for tool kits
NAICS
n/a
SIC 3423: Hand and Edge Tools, Except Machine Tools and Handsaws
Sales Range $50
M
to 100
M
# of Employees 475
Plant Area 175,000
ft2
Annual Production 18,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,703 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,870

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings
01 3.3131: Use evaporation to concentrate material $47,833 $90,000 n/a $(-2,789.0)
(-99,600)
kWh
$(-1,876.0)
-
kW-mo/yr
- $58,248
-
lb
$(-5,750.0)
02 2.1133: Adjust burners for efficient operation $744 $800 - - $744
-
MMBtu
- -
03 2.2511: Insulate bare equipment $1,927 $500 $1,317
47,035
kWh
$610
-
kW-mo/yr
- - -
04 2.4151: Develop a repair/replace policy $199 $289 $119
4,233
kWh
$80
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $50,703 $91,589 $(-1,353.0)
(-48,332)
kWh
$(-1,186.0)
-
kW-mo/yr
$744
-
MMBtu
$58,248
-
lb
$(-5,750.0)
TOTAL IMPLEMENTED $2,870 $1,589 $1,436
51,268
kWh
$690
-
kW-mo/yr
$744
-
MMBtu
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs