ITAC Assessment: NC0223
ITAC logo
ITAC Assessment: NC0223
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Ice
NAICS
n/a
SIC 2097: Manufactured Ice
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 15,000
ft2
Annual Production 110,000,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,914 1,919,314
kWh
Electricity Demand $51,427 6,262
kW-mo/yr
Electricity Fees $4,816 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,229 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,486

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 4.114: Add/modify equipment to improve drying process $1,140 $1,800 $(-22.0)
(-746)
kWh
$(-38.0)
-
kW-mo/yr
$1,200
02 2.4231: Reduce the pressure of compressed air to the minimum required $160 $50 $59
2,020
kWh
$101
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $490 $2,592 $233
7,958
kWh
$257
-
kW-mo/yr
-
04 3.1191: Change procedures / equipment / operating conditions $3,729 $10,000 $2,677
91,367
kWh
$1,052
-
kW-mo/yr
-
05 2.7447: Install vinyl strip / high speed / air curtain doors $186 $500 $130
4,424
kWh
$56
-
kW-mo/yr
-
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,524 $40,000 $2,318
(-24,750)
kWh
$8,206
-
kW-mo/yr
-
TOTAL RECOMMENDED $16,229 $54,942 $5,395
80,273
kWh
$9,634
-
kW-mo/yr
$1,200
TOTAL IMPLEMENTED $1,486 $2,350 $167
5,698
kWh
$119
-
kW-mo/yr
$1,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs