Assessment Year | 2001 |
---|---|
Principal Product | Catalytic converters for boilers |
NAICS |
n/a
|
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
100,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 8,600
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $177,701 | 6,529,015 |
kWh
|
$0.027 |
Electricity Demand | $98,933 | 11,039 |
kW-mo/yr
|
$8.96 |
Electricity Fees | $9,626 | - |
|
- |
Natural Gas | $253,001 | 31,893 |
MMBtu
|
$7.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $195,884 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,699 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4154: Avoid rewinding motors more than twice | $902 | $662 |
$598
23,106
kWh
|
$304
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,475 | $1,464 |
$1,642
63,381
kWh
|
$833
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $340 | $608 |
$226
8,713
kWh
|
$114
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $1,799 | $549 | - | - |
$1,799
-
MMBtu
|
- | - | - | |
05 | 2.2711: Utilize outside air instead of conditioned air for drying | $9,998 | $40,000 |
$14,807
571,706
kWh
|
$8,878
-
kW-mo/yr
|
$(-13,687.0)
-
MMBtu
|
- | - | - | |
06 | 3.3128: Utilize other methods to remove contaminants | $50,246 | $30,000 | - | - | - |
$60,000
-
gal
|
$(-5,000.0) | $(-4,754.0) | |
07 | 4.445: Install equipment to move product | $130,124 | $27,500 |
$746
28,810
kWh
|
$378
-
kW-mo/yr
|
- | - | $129,000 | - | |
TOTAL RECOMMENDED | $195,884 | $100,783 |
$18,019
695,716
kWh
|
$10,507
-
kW-mo/yr
|
$(-11,888.0)
-
MMBtu
|
$60,000
-
gal
|
$124,000 | $(-4,754.0) | ||
TOTAL IMPLEMENTED | $12,699 | $41,211 |
$15,405
594,812
kWh
|
$9,182
-
kW-mo/yr
|
$(-11,888.0)
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs