| Assessment Year | 2004 |
|---|---|
| Principal Product | dog and cat food |
| NAICS | 311111: Dog and Cat Food Manufacturing |
| SIC | 2047: Dog and Cat Food |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
160,000
ft2
|
| Annual Production | 47,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $209,286 | 6,153,960 |
kWh
|
$0.034 |
| Electricity Demand | $141,474 | 16,296 |
kW-mo/yr
|
$8.68 |
| Natural Gas | $455,068 | 78,052 |
MMBtu
|
$5.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,201 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,483 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $1,674 | $2,382 | - | - |
$1,570
-
MMBtu
|
- | - |
$104
-
Tgal
|
|
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,101 | $1,000 | - | - |
$2,101
-
MMBtu
|
- | - | - | |
| 03 | 2.1111: Control pressure on steamer operations | $18,750 | $4,940 | - | - | - | - | $18,750 | - | |
| 04 | 2.2511: Insulate bare equipment | $343 | $263 | - | - |
$343
-
MMBtu
|
- | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $686 | $962 |
$452
13,305
kWh
|
$234
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,946 | $135 |
$1,454
42,720
kWh
|
$748
-
kW-mo/yr
|
- | $(-256.0) | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,093 | $4,412 |
$1,381
40,560
kWh
|
$712
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.7135: Install occupancy sensors | $787 | $1,397 |
$787
23,151
kWh
|
- | - | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,397 | $1,494 |
$1,587
46,683
kWh
|
$810
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 3.3121: Use screening, magnetic separation to remove contaminants | $12,424 | $12,000 |
$2,734
(-80,400)
kWh
|
$(-1,410.0)
-
kW-mo/yr
|
- | - | $11,100 | - | |
| 11 | 4.448: Install automatic part storage / retreval system | $16,000 | $36,000 | - | - | - | $16,000 | - | - | |
| TOTAL RECOMMENDED | $59,201 | $64,985 |
$8,395
86,019
kWh
|
$1,094
-
kW-mo/yr
|
$4,014
-
MMBtu
|
$15,744 | $29,850 |
$104
-
Tgal
|
||
| TOTAL IMPLEMENTED | $39,483 | $43,037 |
$1,906
56,025
kWh
|
$982
-
kW-mo/yr
|
$2,101
-
MMBtu
|
$15,744 | $18,750 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs