| Assessment Year | 2001 |
|---|---|
| Principal Product | Feldspar |
| NAICS |
n/a
|
| SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 31 |
| Plant Area |
50,000
ft2
|
| Annual Production | 440,000,000
lb
|
| Production Hrs. Annual | 8,600
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $387,604 | 9,590,208 |
kWh
|
$0.040 |
| Electricity Demand | $139,948 | 17,773 |
kW-mo/yr
|
$7.87 |
| Fuel Oil #4 | $301,000 | 95,200 |
MMBtu
|
$3.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $169,776 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $111,660 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $272 | $450 |
$214
5,307
kWh
|
$58
-
kW-mo/yr
|
- | - | |
| 02 | 2.4154: Avoid rewinding motors more than twice | $8,087 | $6,437 |
$6,362
157,487
kWh
|
$1,725
-
kW-mo/yr
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,084 | $1,559 |
$3,213
79,530
kWh
|
$871
-
kW-mo/yr
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $44,656 | $40,000 | - | - |
$44,656
-
MMBtu
|
- | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,013 | $35,000 |
$15,209
376,450
kWh
|
$4,286
-
kW-mo/yr
|
$(-5,482.0)
-
MMBtu
|
$(-1,000.0) | |
| 06 | 2.2511: Insulate bare equipment | $9,104 | $17,000 | - | - |
$9,104
-
MMBtu
|
- | |
| 07 | 2.8114: Change rate schedules or other changes in utility service | $90,560 | $35,000 | - |
$90,560
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $169,776 | $135,446 |
$24,998
618,774
kWh
|
$97,500
-
kW-mo/yr
|
$48,278
-
MMBtu
|
$(-1,000.0) | ||
| TOTAL IMPLEMENTED | $111,660 | $76,437 |
$21,571
533,937
kWh
|
$96,571
-
kW-mo/yr
|
$(-5,482.0)
-
MMBtu
|
$(-1,000.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs